Renovation FAQ: Photo Updates

1st Floor stacks are OPEN!  Carpet and new lighting have been installed and the study furniture arrived and is ready for use.  and the stacks are ready for you to browse and retrieve all the books you want!  (no more forms!)

Please remember, that this is considered a "Quiet Study Zone" 

Stacks Entrance

 


If you've been wondering why it has been so noisy in the library this past week . . .  The steel supports for the stairs are being installed and welded into place.    9/21/2021


First of week of the Fall Semester!   8.27.2021


 

6/24/2021   Wow!   
The hole has been cut into the floor in the large reference room to make way for the new stadium stairs and stairwell!   

Making way for the new stairwell


 

Progress!   6/1/2021

 

2nd Floor Stacks.   The book stacks have been covered and wrapped as they begin work on the mechanicals.   New lighting and carpeting will be installed later this summer.